Stabilized armed earth in San Marino
The project
Stabilized reinforced earth wall
Construction of reinforced soil with GREEN STAB PAVE® with on-site soil reuse, stabilized on site with eco-friendly liquid product: fast processing, dust-free, high static and environmental performance.
In the project carried out in San Marino, 540 m³ of soil was treated to build a retaining structure about 3 meters high and 6 meters deep, articulated in 5 successive layers. The soil was of very poor quality, but it was successfully recovered thanks to our liquid stabilization system.
The laying stages:
- Placement of the formwork, geogrid and bio-mat
- laying of 35 cm of soil
- aspersione di GREEN STAB PAVE® diluito in acqua
- soil mixing
- compaction with ram roller
The result: a stable, green, high-performance work that is perfectly integrated into the landscape.